92 GWh
Total announced pipeline
~5 GWh
Expected commissioned 2026
219 MWh
Currently operational
640+
Active tenders in 2026
India BESS Pipeline — Commissioning Progress (2026 Target: 5 GWh of 92 GWh pipeline)
■ Commissioned: ~219 MWh (0.24%)
■ Under construction / near commissioning: ~4.8 GWh (5.2%)
□ Tendered / awarded: ~87 GWh (94.6%)
All Projects
Tender Issued
Awarded
Under Construction
Commissioned
Project Name
Developer / Procurer
MW
MWh
Duration
Location
Chemistry
Status
Tariff / Cost
Announced
Source
NTPC Standalone BESS — Thermal Stations Portfolio
NTPC Ltd (developer TBD)
2,500
10,000
4 hrs
5 NTPC Thermal Stations (states TBC)
LFP (assumed)
Tender Issued
₹5,822 Cr total (Board approved)
Mar–Apr 2026
SolarQuarter
NLC India Solar + Storage — SECI Portfolio
NLC India / SECI
300 MW solar
1,800
6 hrs
TBC (SECI framework)
Not specified
LoA Awarded
—
Feb 2026
Renewable Watch
JSW Energy Standalone BESS — Kerala (SECI/KSEB)
JSW Energy / SECI / KSEB
125
500
4 hrs
Kerala
Not specified
Awarded
₹4.41 lakh/MW/month
2025–26
Energy-Storage.News
Adani Green BESS — Khavda, Gujarat
Adani Green Energy
1,126
3,530
~3 hrs
Khavda, Gujarat
Li-ion (LFP assumed)
Near Commissioning
₹25,000 Cr/yr investment plan
Nov 2025
Energy-Storage.News
Enrich Energy BESS — NTPC Simhadri
Enrich Energy / NTPC
—
290
—
Simhadri, Andhra Pradesh
Not specified
Contract Signed
—
27 Apr 2026
Energetica India
SECI Standalone BESS — Odisha
SECI (developer TBD)
125
500
4 hrs
Odisha
Not specified
Tender Issued
—
2025–26
Mercom India
Himachal Pradesh Solar + BESS
HP State Government
6 MW solar
4.2
2 hrs
Tihra Khas, Himachal Pradesh
Not specified
Tender Issued
—
May 2026
Mercom India
PGCIL BESS — Meghalaya Substations
Power Grid Corporation (PGCIL)
—
TBC
—
Badarpur & Khlerihat, Meghalaya
Not specified
Tender Issued
₹1.007 Cr tender value
May 2026
Indian PSU
Sources: SECI, NTPC, Mercom India, Energy-Storage.News, Renewable Watch, Energetica India. Updated weekly every Monday. Data confidence: Medium–High. ⚠ PGCIL Meghalaya project capacity unconfirmed — may be <1 MWh.